Published on:

19 November 2026

Updated on:

19 November 2026

Read time:

Adrian Batts

Operations Director

If you're planning an office fit out, one of the most common questions you may ask is “how long does an office fit out take?”

An office fit-out programme starts well before construction. Briefing, surveys, design, approvals and procurement all need time before a team can begin transforming the space.

For an illustrative 10,000 sq ft office, a provisional planning allowance of around 24–30 weeks overall, including approximately 12–16 weeks of construction, provides a starting point for discussion. These are illustrative allowances, not a standard OP delivery period. Building condition, specification, approvals and operational requirements can change the programme considerably.

The distinction matters when planning a relocation. A contractor’s construction period does not necessarily include the preparation needed before work starts, or the arrangements required before employees move in.

Here is how the office fit out process comes together, what can overlap and when your decisions will be needed.

Understand the full project timeline

A useful office fit out timeline should distinguish three periods:

  • Preparation: establishing requirements, investigating the building, developing the design, agreeing costs and securing relevant approvals.
  • Construction: carrying out the works, coordinating installations and preparing the space for completion.
  • Readiness for occupation: testing systems, completing handover, preparing employees and managing the move.

Published project durations need the same context. Our 30,000 sq ft headquarters project for Epson in Watford worked to a firm 12-week programme, driven by an expiring lease. The project involved substantial M&E alterations, including a new sprinkler installation.

The case study highlights close coordination with Epson’s decision-makers, technical teams, landlord and building control. It demonstrates how project-specific circumstances and collaboration shape delivery; its published programme should not be treated as the time every organisation needs from initial briefing to occupation.

When comparing programmes, ask what the stated duration includes and which activities must already be complete.

The stages of an office fit-out

Briefing and surveys

Start with the business requirements: who will use the office, how they work, what facilities they need and when the space must be operational.

Surveys and available building information help the project team understand existing services, dimensions, constraints and conditions. Findings may affect both the design and the budget.

Design and costing

Space planning establishes the arrangement of desks, meeting rooms, collaboration areas and supporting facilities. Design development then brings together finishes, furniture, lighting, technology and building services.

Costing should develop alongside these decisions. Our guide to office fit-out costs explains the packages and additional allowances to consider.

Approvals

Identify landlord requirements and any applicable consent or building-control processes early.

Some submissions can progress alongside design development, but their information requirements and review periods need to be understood. The programme should identify which approvals are necessary before particular works proceed.

Procurement

Materials, furniture, equipment and specialist packages need confirmed specifications and delivery dates.

Procurement can overlap with later design activities where the relevant package is sufficiently defined and authorised. Ordering early without resolving requirements can introduce the risk of unsuitable products or subsequent changes.

Construction

Site activities may include protection, strip-out, services alterations, partitions, ceilings, finishes and installations.

These activities follow dependencies. Some can overlap in separate areas, while others need preceding work to be complete. Access, deliveries and specialist attendance need coordination throughout.

Commissioning and handover

Commissioning checks that installed systems operate as intended. Handover brings together inspections, documentation, demonstrations, training and arrangements for outstanding items.

Plan these activities before construction finishes. A completed-looking office still needs working connectivity, usable meeting-room technology and a prepared facilities team.

26 11 Your office fit out journey

An illustrative office fit-out programme

The example below assumes a 10,000 sq ft London office, approximately 929 sq m, receiving a Category B fit out within an existing Category A space.

It assumes vacant possession, usable base-building services, no major structural alterations, normal working hours, timely client decisions and products available within the planned procurement periods.

It is a hypothetical planning exercise, separate from the Epson case study, rather than an OP project commitment.

ActivityIllustrative timingHow it connects
Briefing, surveys and initial budgetWeeks 1–4Establish requirements and investigate the space
Concept design and layoutWeeks 3–6Can develop as survey information becomes available
Technical design, specification and costingWeeks 6–10Coordinate services and confirm package requirements
Landlord and applicable approvalsWeeks 6–12Assumes required approvals are resolved before affected works
ProcurementWeeks 10–22Order agreed packages for their required installation dates
ConstructionWeeks 13–26Sequence works and coordinate deliveries
Commissioning and handoverWeeks 25–27Begin checks in completed areas where appropriate
Programme contingency and move preparationWeeks 28–29Protect readiness and resolve remaining issues
Target occupationWeek 30Subject to the space being ready for safe, operational use

The rows should not be added together: several activities overlap.

Approval periods and supplier lead times must be checked for the actual project. An item needed near the beginning of construction cannot be scheduled on the same basis as furniture arriving towards the end.

Floor area alone does not determine duration. The number of rooms, services alterations, specification and delivery arrangements also influence the office fit out programme.

What can affect delivery?

Landlord approvals and building constraints. Missing information, requested revisions, restricted access or unexpected conditions can affect the sequence. Establish responsibilities and access arrangements early.

Client decisions. An unresolved layout or specification can hold up technical coordination, costing and orders. Agree named decision-makers and realistic response dates.

Design changes. Moving a meeting room after related services have been coordinated may affect several packages. Review the time and cost implications before authorising changes.

Long-lead items. Bespoke joinery, specialist equipment or selected furniture may require ordering well before installation. Confirm lead times and suitable alternatives during design.

Occupied offices. Phased works can introduce repeated moves, restricted working areas and planned service interruptions. Our phased office fit-out guide explains the operational considerations.

These are risks to investigate, rather than reasons to assume every project will be delayed.

 

What does the client need to decide, and when?

Your decisions help the project team maintain a coordinated programme.

DecisionWhen it is needed
Business brief, occupancy and essential facilitiesAt the start, before detailed planning
Budget and contingency approachEarly enough to guide design and procurement
Layout and room requirementsBefore related technical design is finalised
Finishes, furniture and equipmentBefore package orders are authorised
IT, AV and access-control requirementsDuring design coordination, before infrastructure is fixed
Move arrangements and operational prioritiesBefore the final delivery and handover sequence is agreed

Identify who can approve each decision and who needs to contribute. Bringing finance, facilities, IT and employee representatives into the relevant discussions early can help avoid conflicting requirements later.

Work backwards from your occupation date

Begin with the date employees need a functioning workplace, then identify the milestones required to achieve it.

Allow time before occupation for move preparation, operational testing, training and any essential issues that need resolving. Work backwards through construction, delivery dates, procurement and approvals to establish when design decisions must be made.

Keep lease commitments, existing-premises obligations and landlord access dates visible alongside the fit-out programme.

Contingency should reflect the project’s risks. A building with incomplete information or an occupied refurbishment may need a different allowance from a straightforward vacant-space project. Agree where that allowance sits and review it as uncertainties are resolved.

If the required date cannot be achieved comfortably, discuss the options early. These might include changing the scope, selecting different products or planning a staged move.

At OP, we coordinate workplace design and project delivery around the requirements of the business. Speak to our team early about your intended occupation date, so we can help establish the information, decisions and milestones needed for a realistic office fit out programme.

A successful office fit out is a meticulous alignment of vision, design, project management, and client needs. While every business and building has unique considerations, our experience creating workspaces provides clients invaluable guidance with navigating the process. We collaborate to balance expediency with quality, setting realistic schedules that actualise inspired spaces on time and on budget.

Adrian Batts, Operations Director

While variables like size and building constraints make predicting exact office fit out duration difficult, the above outlines average fit out timelines. As experienced designers and fit out specialists, OP use this expertise to guide clients through the process smoothly.

Need help planning your office fit out? Reach out to our team of experts at Office Principles. We’ll collaboratively transform your workspace vision into an inspired reality.

Ready to transform your workplace

Get in touch for advice on your project

Meet the Author

With over two decades experience of the industry, working across a diverse mix of projects in a full range of roles, Adrian has a unique understanding of office fit out methodology; the strategic planning of a project and its design and cost-planning. He is passionate about formulating the best workplace strategies for all clients, applying the core principals of change management to provide positive outcomes for the end-user.